Please note that the schedule below is subject to change.
Availability of Construction
January 4
Mobilization and Materials
January 4-17
Vance Street
January 18-Febrary 28
Oak Avenue
March 1-31
West Avenue
April1-30
West B Street
April 26-April 30
S. Main Street
May 1 – June 21
West A Street
June 21 – July 22
Testing and Reconnections
July 22-August 2
Final Paving and Cleanup
August 3 – September 1
Anticipated Completion
September 1