Schedule

Please note that the schedule below is subject to change.

Availability of Construction

January 4

Mobilization and Materials

January 4-17

Vance Street

January 18-Febrary 28

Oak Avenue

March 1-31

West Avenue

April1-30

West B Street

April 26-April 30

S. Main Street

May 1 – June 21

West A Street

June 21 – July 22

Testing and Reconnections

July 22-August 2

Final Paving and Cleanup

August 3 – September 1

Anticipated Completion

September 1