We are getting close to the end of the project, but we did find a surprise that we need to address.  We will need to add another pipe on West Avenue to supply some of the buildings near the public restrooms.  We will be performing that work Tuesday through Thursday.  We are going to continue to patch the sidewalks and curb and gutter that we had to remove during the project as well as continue to clean up the project.

The schedule is as follows:

  • Monday  - No Closures.  We will be working in the Vance St/West Ave intersection.
  • Tuesday  - West Ave will be closed between First St and West A St for traffic traveling south.
  • Wednesday  – West Ave will be closed between First St and West A St for traffic traveling north.
  • Thursday  - No Closures.  We will be working in the parking spaces on West Ave near the public restrooms
  • Friday  - No Closures.  We will be working in various locations on the project.
Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.